Mutapa accelerates push for lithium processing
Mutapa Energy Resources is racing to set up lithium processing at Sandawana Mines in Mberengwa before the December 2026 ban on raw concentrate exports takes effect.
Mutapa Energy Resources is racing to set up lithium processing at Sandawana Mines in Mberengwa before the December 2026 ban on raw concentrate exports takes effect. The state-owned company has told parliament it is behind schedule on building a sulphate plant that would turn the mineral into a higher-value product. It is also pushing ahead with a concentrator plant that will cost between US$315 million and US$330 million and handle three million tonnes of ore a year.
If you earn money from mining shares, supply contracts or local jobs tied to Sandawana, the delays matter. The firm has raised only US$20 million of the US$200 million it first hoped to get from Zimbabwean investors. That shortfall has forced it to turn to Chinese partners for the bulk of the cash. Every month the project slips, the mine keeps sending raw material abroad and loses the extra dollars that local processing would bring home.
Sandawana has already pulled 2.9 million tonnes of ore from its starter pit since January at an average grade of 1.48 percent. So far it has relied on toll processing at Gwanda Lithium Company, which has treated 310,000 tonnes of its concentrate. The company has spent more than US$65.3 million on supporting works, including a 52-kilometre access road, a power line and a water pipeline. These are sunk costs that must be recovered from future sales of processed lithium.
Chief executive Innocent Rukweza told the Parliamentary Portfolio Committee on Mines and Mining Development that talks are under way to start sulphate-plant construction next year. He warned that high taxes, export rules, red tape and unreliable electricity are making it harder to attract the money needed. The government wants the wider mining industry to earn US$12 billion this year, with more of that cash staying in the country through local beneficiation.
The mine is wholly owned by Mutapa Energy Resources, which falls under the Mutapa Investment Fund. Committee chairman Remigio Matangira said the project should create jobs and bring corporate social spending to Mberengwa.
The next milestone is the start of sulphate-plant construction in 2026. Until then, the funding gap will decide how much extra value Zimbabwe captures from its lithium.
- Zimbabwe's Sandawana Breaks Ground On U.S.$330m Lithium Plant Ahead of Export Ban
- Mutapa Energy Drives Digital Modernisation in Rural Mberengwa
- Mutapa Energy seeks government backing for Sandawana mines
- Hwange power expansion sparks industry revival
- Mutapa Energy takes digital education drive to rural Mberengwa