ZESA announces contingency plan ahead of Hwange unit 7 & 8 two-month shutdown

ZESA will shut down Units 7 and 8 at Hwange Power Station for planned maintenance starting on 15 November 2026.

Companies and Investment Finlede

Sign in to save this story

ZESA will shut down Units 7 and 8 at Hwange Power Station for planned maintenance starting on 15 November 2026. Unit 7 is due back on 4 January 2027 and Unit 8 on 26 January 2027. The power utility said the two-month outage forms part of routine work to keep the plant reliable and cut the chance of sudden breakdowns later.

The move will cut domestic coal-fired generation for most of the peak holiday period. ZESA has lined up extra output from Kariba Power Station during high-demand hours, more imports from the Southern African Power Pool, and additional supplies bought from independent power producers under existing power-purchase agreements. It will also bring on new solar projects as they connect to the national grid.

The timing helps. Electricity demand usually drops in the coming weeks, which should limit the strain on the system. ZESA described the shutdown as a standard part of its asset-management programme rather than an emergency fix.

Advertisement

As Finlede reported in March, the same two units have already saved the country US$92 million in foreign currency by cutting the need for imports since they came online. Their temporary absence means Zimbabwe will once again rely more heavily on Kariba, regional purchases and private producers to keep the lights on.

For households and businesses the immediate risk is longer or more frequent power cuts if the extra supplies fall short. Those who run generators or solar backups will face higher fuel and maintenance bills during the outage. Factories and mines that pay for uninterrupted supply through special contracts may see those costs rise as ZESA leans on costlier imported power.

The utility insisted that the measures already in place will keep supplies stable. The next date to watch is 4 January 2027, when the first unit returns and domestic capacity begins to recover.

Advertisement
Reported from:

Something in this story need updating? Ask for a correction.

The morning digest

The day's money stories, before work

One message each morning with the stories that matter. Free, and one tap to stop.

Prefer your phone? Get it on Telegram.
Your story

Have a story for us?

News about money, business or prices where you are. Tell the newsroom and we will look into it.

Tell us your story