Zimbabwe has gone 304 days without load-shedding.
Zimbabwe has gone 304 days without load-shedding. The country needs only 61 more days to hit a full year without scheduled power cuts, a milestone expected around 27 December. This would be the first time in more than 20 years that the country has managed 365 consecutive days without rationing electricity.
Improved output at Hwange Thermal Power Station and Kariba South Power Station has kept the lights on. As of yesterday the country was producing 1,455 megawatts, with Hwange contributing 994MW, Kariba 415MW and independent power producers 46MW. ZESA Holdings told The Herald that recent outages in Budiriro, Glen View, Highfield, Kuwadzana and Shamva were caused by faults and planned maintenance, not load-shedding.
The gains have held through the entire winter of 2026, the first time this has happened in more than two decades. ZESA stakeholder relations officer Prisca Utete said the utility is monitoring plant outages and network faults closely. Electricity imports and output from independent producers have also helped fill gaps.
Yet the picture ahead is tighter. The Zambezi River Authority has cut the water allocation for power generation at Kariba in 2027 to 23 billion cubic metres, down from 36 billion this year. Zimbabwe Power Company and Zambia's ZESCO will each receive 11.5 billion cubic metres. The decision follows forecasts of below-normal rainfall linked to El Niño.
As of 14 October, Zimbabwe still had 6.13 billion cubic metres left in its current allocation, or 34 percent. Zambia had used more of its share. ZESA says it is working with the Zambezi River Authority to conserve water at Lake Kariba. The utility also plans to run Hwange harder, import power through the Southern African Power Pool when needed, and push for more solar projects.
A builder in Cape Town saving for a stand back home knows families there have faced fewer blackouts this year. A pensioner waiting on NSSA has had more reliable power for daily needs.
Sustaining the record will test ZESA. Lower water at Kariba next year means thermal power and imports must carry more of the load. The next number to watch is whether the country reaches that 365-day mark on 27 December.
- ZESA claims Zimbabwe has gone 304 days without load-shedding
- Zimbabwe Captive Power and National Grid Benefits
- Zimbabwe exporting power surplus to regional grid, says Murwira
- ZESA posts US$139.3 million profit
- ZESA Holdings re-bundles in sweeping executive shake-up
- ZPC Invites Bids for Threadb Tape and Safety Goggles at Kariba South
- Zimbabwe Power Company Invites Bids for Supply of Mechanics Marking Blue to Kariba
- ZPC Seeks Gasket Rubber Insertion for Kariba South Power Station